Rebuild Update

And up it goes…

With the development of the new school going full steam ahead we are seeing a huge amount of construction and ongoing works. Here’s an overview of the current works.

Main works for August 2018
Main Teaching Block & Gym

  • Complete secondary steel installation, lintols, stubs and balcony
  • Ongoing installation of gas membranes Level 1
  • Backfill combined service trench installation East Wing in new main teaching block
  • Pour Level 1 remaining slab
  • Erect the precast panels and structural steel to Gym
  • Curtain wall installation for new main teaching block
  • South wall and roof cladding installation ongoing for August
  • First fix service installation – fire, electrical, mechanical (ongoing)
Whare Oho & Whare Tapere
  • Pour Level 1 concrete slab
  • Whare Oho precast panels and structural steel installation
  • Complete the combined service trench installation for Whare Tapere
  • Complete the insitu foundations for Whare Tapere
  • Complete gas membranes to Whare Oho slab and foundations
  • Reinstate the roading around old F Block following F Block demolition

August Site Works and Demolition
  • Old F Block demoliltion
  • Continue central driveway services
  • Commence hard landscaping to central driveway and grassed area post F Block demolition.

 

You will see in the photos the large crane installing the side panels of the new main teaching block. The new F Block (Technology Classrooms) are now fully operational . The library has undergone a transformation to allow space for the new outdoor patio area for the new school.
Our Principal Ivan Davis has been giving onsite tours to teaching staff for them to see their new learning environments and you will see Renae Liao checking out her new teaching space for the Languages Department.
  
Jessie Bernard
Health & Safety Manager