Here’s an update of the works inside the build sites for June.

Main Block
– Level 3 final floor concrete pour on Monday 18th June
– Final main block roof steel installed commencing 14th June
– Prepare scaffold for installation of main block roof
Whare Tapere
– Foundations to complete in coming weeks.
Temporary F Block
– Complete fit out for Block F relocatable buildings by Sunday 24th June
– Soft Technology is now located in the lower D Block levels in D1 and D2
– Site fencing to be reconfigured around F Block.

Site offices at the back of the building compound site

Jessie Bernard
Health & Safety Manager