Our Solar Power Legacy
Be part of something positive, a good news story. WSCW’s solar project is forging ahead! We have had 126 panels donated by whanau, businesses, alumni and even sports teams. Our…
Principal’s Notes
What an absolute pleasure it has been to introduce our students and then the community into our new school. They joy of seeing our students adapt so quickly to the…
Rebuild Update
The only way is up..... Waiorea Build Sites (Whare Tapere, Whare Ako) - Roofing is being completed. New Main Teaching Block - glazing (windows). Gymnasium - Finishing level 2 flooring…
Becoming a new school
Here are four published documents that explore the ILE model. Please download and have a read for an enlightening look into what the future holds for Springs. The impact of physical…
Rebuild Update
Here is an update of the rebuild over the past few weeks and what is planned for the next 4 weeks. Waiorea Build Site (Whare Tapere, Whare Ako) - ongoing works…
Careers/Rebuild/Health & Safety
On Wednesday in the library we hosted a Careers Seminar for senior students wanting to look into the world of Engineering, Construction and Trades associated with our own development -…
Rebuild Update for Newsletter
There is a significant increase in the works for the rebuild of the school with a hype of activity. Rebuild update Waiorea Build Site (Whare Tapere, Whare Ako) - ongoing…
Principal’s Notes
Let’s start this month with the power cut at the beginning of last week! I believe Western Springs College and the Zoo both made midday news on TV1 as a…
Rebuild Update
Here's an update of the works inside the build sites for June. Main Block - Level 3 final floor concrete pour on Monday 18th June - Final main block roof steel installed…
Principal’s Notes
The old saying “a picture is worth a thousand words” comes to mind as I look through the excited smiles and beaming faces as our students met the Prime Minister…
Closure of MOTAT Driveway
We have received the following communication from MOTAT. “We would appreciate it if you could advise your community that the driveway is no longer accessible for public thoroughfare and…
Principal’s News
Foundations set for the big build After 9 months of site preparation, building proper has begun at the school with foundations, footings and reinforcing steel in the new main teaching…